  1. Melrose Drive Reconstruction
  2. State Route 3 Culvert Replacement
  3. State Route 101 Culvert Replacement
  4. Township Road 119 Bridge Replacement
  5. Garfield - McKinley Road Reconstruction
  6. Mastodon Wetland Restoration
  7. US 224 Culvert Replacement
  8. County Road 292 Relocation
  9. TR 299 Road Improvements
  10. Gay Street Improvement Project
  11. Menards-Walker Lake Road
  12. Reid Industrial Park Phase 2
  13. Day Road Bridge Replacement

Melrose Drive Reconstruction

Client :: City of Wooster
Location :: Wooster, Ohio


Description of Work Performed ::





State Route 3 Culvert Replacement

Client :: Ohio Department of Transportation
Location :: Creston, Ohio


Description of Work Performed ::





State Route 101 Culvert Replacement

Client :: Ohio Department of Transportation
Location :: Clyde, Ohio


Description of Work Performed ::





Township Road 119 Bridge Replacement

Client :: Wayne County Commissioners
Location :: Baughman Township, Ohio


Description of Work Performed ::





Garfield - Mckinley Road Reconstruction

Client :: City of Newark, Ohio
Location :: Newark, Ohio


Description of Work Performed ::





Mastodon Wetland Restoration

Client :: Flying Horse Farm
Location :: Mt. Gilead, Ohio


Description of Work Performed ::

  • - 108,798 CY of Excavation
  • - Erosion Control
  • - De-watering of 10 acre lake
  • - Created 21 acre wetland

US 224 culvert Replacement

Client :: Ohio Department of Transportation
Location :: Greenwich, Ohio


Description of Work Performed ::





County Road 292 Relocation

Client :: Holmes County Airport Authority
Location :: Millersburg, Ohio


Description of Work Performed ::





TR 299 Road Improvements

Client :: Baughman Township Trustees
Location :: Baughman Township, Wayne County, Ohio


Description of Work Performed ::

  • -Clearing and grubbing
  • -5,429 cubic yards of excavation and 1,899 cubic yards of embankment
  • -5,095 square yards of sub grade compaction
  • -Erosion control and seeding
  • -Installation of 758 linear feet of new storm sewer with 4 new catch basins
  • -741 Cubic yards #2 and 304 Limestone aggregate base
  • -Sub grade stabilization and geogrid

Airport West Industrial Park

Client :: City of Mansfield
Location :: Mansfield, Ohio


Description of Work Performed ::

  • -Clearing and grubbing for development of new industrial park
  • -19,700 cubic yards of excavation and 5,183 cubic yards of embankment
  • -12,505 square yards of sub grade compaction
  • -2,084 cubic yards of aggregate base
  • -Curb and gutter and new pavement
  • -Installation of 3,800 Linear Feet of RCP ranging in size from 12” to 72”
  • -Installation of 23 catch basins and 16 manholes
  • -9,784 linear feet of under drains with fabric wrap
  • -Erosion control and seeding

Gay Street Improvement Project

Client :: City of Mount Vernon
Location :: Mount Vernon, Ohio


Description of Work Performed ::

  • -Street replacement of approximately 8,939 SY of brick street
  • -Brick pavement removal
  • -Excavation and export
  • -304 limestone base
  • -1,031 Linear Feet of storm sewer including 31 structures and 3,097 Linear Feet of under drains
  • -1,747 Linear Feet of 8” Ductile Iron Pipe class 52 waterline including valves, hydrants, connections, and services.
  • -Signalization and signage
  • -Traffic control and erosion control

Menards-Walker Lake Road

Client :: FH Martin Constructors
Location :: Ontario, Ohio


Description of Work Performed ::

  • -12.5 acre commercial site package
  • -Fine grading sub grade compaction
  • -Placing and fine grading approximately 30,000 tons of 304 limestone
  • -Road extension, widening and intersection improvement
  • -Excavation and export
  • -New storm sewer and under drains
  • -Traffic signalization and traffic control
  • -Erosion control

Reid Industrial Park – Phase 2

Client :: City of Mansfield
Location :: Mansfield, Ohio


Description of Work Performed ::

  • -19,018 Cubic Yards of excavation
  • -14,894 Cubic Yards of export
  • -18,228 Square Yards of sub grade compaction
  • -3,868 Linear Feet of storm sewer and 7,683 Linear Feet of under drains
  • -3,400 Cubic Yards of 304 limestone base
  • -2,651 Linear Feet of 15” SDR 26 sanitary sewer including manholes
  • -2,471 Linear Feet of 16” Ductile Iron Pipe class 53 including valves and hydrants

Day Road Bridge Replacement

Client :: Richland County
Location :: Richland County, Ohio


Description of Work Performed ::

  • -Temporary road construction and barrier wall
  • -Cofferdams and structure removal
  • -Excavation
  • -Installed 99 Linear Feet of 20’7” x 5’3” aluminum box culvert